Wednesday, April 12, 2023
Bricks Complete
We lost a few weeks in the bricking phase, but we're done. All up, the bricks took ~5 weeks. They're looking generally good. There are a number of defective bricks that will need to be replaced. The plan is to do the brick clean and then inspect and address any defects.
Roofing was meant to start this week. It's been delayed due to the incorrect fascia boards arriving on site. Hopefully it will resume quickly next week.
Subscribe to:
Post Comments (Atom)
Happy Handover!
All done and looking great. A great job from Clarendon and Scott, our site supervisor!
-
All done and looking great. A great job from Clarendon and Scott, our site supervisor!
-
Clarendon has a neat facade builder on their website that lets you visualise roughly what the home will look like. It doesn't have all ...



No comments:
Post a Comment